Quebec Street Construction - Progress Report - Oct. 20 to Oct. 31, 2025
Quebec Street Construction - Progress Report - Oct. 20 to Oct. 31, 2025
Preparation for concrete work was completed last week. On October 15th the concrete contractor began to work on installing new curbs.


Crews have begun setting forms and pouring the sidewalk.


Several concrete steps required removal and new concrete steps have been poured. As the crew complete the sidewalk pour, QBT are busy preparing for asphalt.



The anticipated start date of the base asphalt is Friday, October 24th, with the top coat of asphalt the following week. During this time QBT will fine grade the road and complete touch up landscaping as required.
Sign up to our Newsletter
Stay up to date on the township's activities, events, programs and operations by subscribing to our eNewsletters.