With road preparation complete on Quebec Street, the base coat of asphalt is to be applied today, Friday, October 24, 2025. After which, raising the manhole frames/covers to final grade and grinding the lap joints will take place. The top lift of asphalt is scheduled to be done on Wednesday, October 29, 2025, weather permitting.
Both the grinding and paving operations will result in encroaching on Hwy 7. This will cause a minor detour on Hwy 7. This is similar to previous detour, however not as extensive.
PLEASE use extreme caution in this area. Construction flaggers will be directing traffic, please pay close attention.