Quebec Street Construction Report - Oct 3rd, 2025 to to Oct 17th, 2025
Construction Progress Report - Oct. 3rd, 2025 to Oct 17th, 2025
There we have it everyone, the final watermain connection to the existing. This now finishes the underground work, including the storm and sanitary sewers.
Work will now proceed to the completion of the road granulars, and preparation for the concrete curb and gutter as well as the sidewalks. Excess materials will be cleaned up as well.
At present the work is expected to be complete by October 24, 2025.
Please direct questions or escalate emergencies to the contact list below:
Mike Walsh, Supervisor, (613) 827-4445
Brian Wood, Foreman, (613) 885-1504
Kevin Harnden, Project Manager, (613) 970-2121
Drew Sinclair, (613) 827-4525